Lynn Creek Crossing Update

Road1  Road2

Pictured above left is Crow Paving Project Superintendent, Monroe Thomas. The dirt work is nearly finished and the road is within one foot of final height.  The next task will be application of 8 inches of gravel.  Still to be done are the wings for culverts, reenforcement of the dirt work with riprap rock, asphalt paving, and guard rail installation.  With a winter that has been anything but normal, the new projected completion date is March 21st.  After the gravel is applied many of the remaining tasks require temperatures at 45 degrees or higher.