20131112_083420Work has begun in earnest on the raising of Lynn Creek Crossing on West Cliff Drive. Most of the old culvert tubing has been removed and the bed is being prepared for the new precast concrete culverts that will be set in place. The new culverts are currently being poured and prepared for shipment to Fairfield Bay. Once they begin arriving, they will be put into place using a large crane. Some fill is already being moved to widen the base of the road bed in order to allow it to be raised. The target date for completion is on or before February 28. Photo courtesy of Gail Carlo